THEORY AND PRACTICE OF ENGINEERING.

Book II.

Labour for a Cube Metre of Sleepers tenoned and mortised to the heads of piles, andhalved at the ends to the cappings; the piles being at the same distance, and the scantlingof the timber as before, each sleeper being 5 metres long.

Hours of aCarpenter.

8 mortices and tenons as above - 26-00 ~]

4 halvings at 5 hours each - 20-00 l 49-00

Placing and adjusting ----- 3-00 J

Labour for a Cube Metre of binding Pieces, let into the piles, and bolted to

8 notches or halvings at an hour each - 8-00

8 holes for bolts, each 50 centimetres in length, giving 4metres at the rate of 3 hours for piercing on the plane,and fixing the bolt ----- 12 00

2 joints at the end, 2*50 each - 5*00

Placing and adjustment ----- 2*00

them.Hours of aCarpenter.

. 27*00

Labour for a Cube Metre of Capping or Sleepers, fixed to the piles by iron

8 bolt-holes 30 centimetres in length, giving together 2*4

metres, at the rate of 1 hour each for piercing - 2*40

8 iron pins, driven in at 0*15 hour for each - 1 *20

Placing and adjustment ----- 200

pins.

Hours of aCarpenter.

5*60

Fur the Labour when the Sleepers are under Water.

Piercing the holes

8 iron pins driven in, 0-50 hour eachPlacing and adjustment

2*404 00400

Hours of aCarpenter.

I 10-40

Labour for a Cube Metre of Platform, with deals or planks,10 centimetres, and their width 25 centimetres.

8 metres of joints in length to prepare, forming 0*8 squaremetres, at the rate of 0*15 of an hour per square metrePlacing and adjusting a square metre of HoorWhich amounts per cube metre to -

the thickness of which are

1 200-90

Hours of aCarpenter.

I 1*20

21 *00

The Labour when the Deals are framed together , and afterwards sunk under water.

Preparing the edges and adjusting the planks as beforeSinking and placing under water - - - -

Which amounts per cube metre to -If the platforms are in compartments, add per squaremetre ------

And per metre cube -

2-10

1*00

}

Hours of aCarpenter.

3*10

31*00

0*15

1*50

Labour on Timber in the Yard. — The first operation is tracing the form by applyingthe mould, and ascertaining the proper timbers for the purpose; so that none be selectedthat would occasion much waste; it is then sawn, and the face over which the saw haspassed is considered perfect; hence, there is economy in the employment of large timbers :if the faces are dressed with the axe or the adze, and the deals are formed from large tim-bers, then

Hours of aCarpenter.

To select a cube metre of timber apply it to the mould, *1

and line it out, for the least - - - - 3-00 l 4-50

for the most - - - - 6*00 I

As for the cutting, it must be estimated according to the nature of the works, they beingtoo various to be analysed: some general results will enable a judgment to be formed,which may approximate near enough for practice.

For the labour employed in cutting a cube metre of timber for the principals of a bridge,the total length of which is 36 metres, the scantling 30 centimetres, which form a cube of3-24 metres.

For cutting a Cube Metre of Timber at the Yard. — Timber not wrought when used forcentres or temporary bridges.